[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92818,64,1,"单选题","某工程双代号网络计划中，工作E的持续时间为7天，总时差为5天，其最早完成时间是第12天，则工作E的最迟开始时间是第()天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","9",false,{"key":16,"text":17,"correct":18},"B","10",true,{"key":20,"text":21,"correct":14},"C","11",{"key":23,"text":24,"correct":14},"D","12","此题考查最迟开始时间参数计算。工作的总时差等于该工作最迟完成时间与最早完成时间之差，或该工作最迟开始时间与最早开始时间之差。本题中，工作E的总时差=工作E最迟完成时间-工作E最早完成时间，故工作E最迟完成时间=5+12=17(天)。工作E的最迟开始时间=工作E最迟完成时间-工作E持续时间=17-7=10(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]