[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92817":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92817,64,1,"单选题","所谓双代号网络计划，是以箭线及其两端节点编号表示工作的( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本计划",false,{"key":16,"text":17,"correct":18},"B","进度计划",true,{"key":20,"text":21,"correct":14},"C","质量控制计划",{"key":23,"text":24,"correct":14},"D","合同管理计划","此题考查对双代号网络计划的理解。双代号网络计划又称箭线式网络计划，是以箭线及其两端节点编号表示工作的进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]