[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92815":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92815,64,1,"单选题","若某工程网络计划的计算工期等于计划工期，则该网络计划中的关键工作是（）的工作。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","时标网络计划中没有波形线",false,{"key":16,"text":17,"correct":14},"B","与紧后工作之间时间间隔为零",{"key":19,"text":20,"correct":21},"C","最早完成时间等于最迟完成时间",true,{"key":23,"text":24,"correct":14},"D","开始节点与完成节点均为关键节点","本题考查的是网络计划时间参数的计算。当计算工期等于计划工期时，关键工作的总时差为0，即最迟完成时间等于最早完成时间。从终点到起点不出现波形线的线路即为关键线路。关键线路全由关键工作构成且所有工作之间的时间间隔均为零。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]