[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92813":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92813,64,1,"单选题","在网络计划实施过程中，当某项工作进度比原计划最早开始时间拖后，拖延的时间刚好等于其总时差，则该工作（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不影响其紧后工作的最早开始时间",false,{"key":16,"text":17,"correct":14},"B","必将影响工程总工期",{"key":19,"text":20,"correct":21},"C","不影响其紧后工作的最迟开始时间",true,{"key":23,"text":24,"correct":14},"D","对其后续工作及工程总工期均无影响","这种情况下不影响总工期，即不影响其紧后工作的最迟开始时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]