[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92811":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92811,64,1,"单选题","在网络计划执行过程中，发现A工作还需工作6天，但至该工作最迟完成时间尚有4 天，则该工作（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超前2天",false,{"key":16,"text":17,"correct":18},"B","影响总工期2天",true,{"key":20,"text":21,"correct":14},"C","影响总工期4天",{"key":23,"text":24,"correct":14},"D","影响总工期6天","该工作超过最迟完成时间2天，就会耽误2天工期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]