[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92807,64,1,"单选题","某工程单代号网络计划中，工作G的最早开始时间为第18天，持续时间为5天，工作G有三项紧后工作，其最早开始时间分别为第28．30和32天，则工作G的自由时差是（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","7",false,{"key":20,"text":21,"correct":18},"C","9",{"key":23,"text":24,"correct":18},"D","10","工作G的最早完成时间=最早开始时间+持续时间=18+5=23(天)。 工作G的自由时差=Min(28，30，32)-23=5(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]