[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92805":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92805,64,1,"单选题","工作E是某工程网络计划中的非关键工作，在该计划执行过程中，工作E的实际进度比计划进度拖后，且拖后的时间超过了其自由时差，则工作E将影响（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","紧前工作的最迟开始时问",false,{"key":16,"text":17,"correct":18},"B","紧后工作的最早开始时间",true,{"key":20,"text":21,"correct":14},"C","紧后工作的最迟开始时间",{"key":23,"text":24,"correct":14},"D","后续工作的最迟完成时间","进度拖延的时间>自由时差时，影响其紧后工作的最早开始时间；进度拖延的时间>总时差时影响总工期，影响的时长是相应二者的差值。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]