[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92799,64,1,"单选题","某单代号网络计划中．工作N与其紧后工作 H、M的时间间隔分别为5周和3周，工作H和M的总时差分别为2周和6周，则工作N的总时差是（）周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","9","在单代号网络计划中，工作的总时差：Min(与其紧后工作的时间间隔+相应紧后工作的总时差)=Min(5+2，3+6)=7(周)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]