[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92796":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92796,64,1,"单选题","某项工作估计可能完成的最长时间为18天，最短为14天，最有可能的时间为16天，则该工作的持续时间为（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":18},"B","16",true,{"key":20,"text":21,"correct":14},"C","17",{"key":23,"text":24,"correct":14},"D","18","采用三时估算法，估算该工作持续时间：(18+4×16+14)÷6=16(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]