[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92794":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92794,64,1,"单选题","下列有关工程网络计划叙述正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总时差为零的工作为关键工作",false,{"key":16,"text":17,"correct":14},"B","关键线路上不允许有虚工作的存在",{"key":19,"text":20,"correct":14},"C","自由时差为零时，总时差必为零",{"key":22,"text":23,"correct":24},"D","除了以网络计划终点为完成节点的工作．其他工作的最迟完成时间应等于其紧后工作最迟开始时间的最小值",true,"当且仅当网络计划的计算工期等于计划工期，关键线路的总时差为零，选项A有误；关键线路上允许虚工作存在，选项B有误；自由时差小于等于总时差，因此总时差为零，自由时差必为零，但自由时差为零，总时差未必为零，选项C有误。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]