[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92786,64,1,"单选题","网络计划中，工作M的最早开始时间是第8天，持续时间为5天．该工作有三项紧后工作，其最早开始时间分别为第16、18、21天，则工作M的自由时差是（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","10","工作的自由时差=本工作紧后工作最早开始时间的最小值-本工作的最早完成时间。本工作的最早完成时间=本工作的最早开始时间+本工作的持续时问。M的自由时差=Min(16，18，21)-(8+5)=16-13=3(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]