[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92782":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92782,64,1,"单选题","在双代号网络计划中，某工作的最迟完成时间等于其所有紧后工作（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最迟完成时间的最小值",false,{"key":16,"text":17,"correct":18},"B","最迟开始时间的最小值",true,{"key":20,"text":21,"correct":14},"C","最迟完成时间的最大值",{"key":23,"text":24,"correct":14},"D","最迟开始时间的最大值","在双代号网络计划中，某工作的最迟完成时间等于其所有紧后工作最迟开始时间的最小值。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]