[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92780,64,1,"单选题","某工程双代号时标网络计划中，工作H有三项紧后工作，其工作总时差分别为4．6和7周，工作H的自由时差为2周，则工作H的总时差是（）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":18},"B","6",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","9","工作H的总时差为：Min(4，6，7)+2=6(周)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]