[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92776":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92776,64,1,"单选题","某项工作有3项紧后工作，其持续时间分别为4天、5天、6天；其最迟完成时间分别为19天、16天、15天，本工作的最迟完成时间是（）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","11",{"key":19,"text":20,"correct":21},"C","9",true,{"key":23,"text":24,"correct":14},"D","6","三项工作的最迟开始时间分别为：19-4=15(天)；16-5=11(天)；15-6=9(天)，选最小值9天即为本工作的最迟完成时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]