[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92774,64,1,"单选题","网络计划中的关键线路是指由（）构成的贯穿起终点的线路。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","关键节点",false,{"key":16,"text":17,"correct":14},"B","总时差为零的工作",{"key":19,"text":20,"correct":14},"C","自由时差为零的工作",{"key":22,"text":23,"correct":24},"D","总时差最小的工作",true,"本题考查关键线路的概念。在双代号网络计划中，工作总时差最小的工作是关键工作。自始至终全部由关键工作组成的线路为关键线路，或线路上总的工作持续时间最长的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]