[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92772,64,1,"单选题","某工程网络计划中，工作D有三项紧前工作，其最早开始时间分别是第25周、第21周和第19周，三项工作的持续时间分别是3周、8周和7周，则工作D的最早开始时间是第（）周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","26",false,{"key":16,"text":17,"correct":14},"B","28",{"key":19,"text":20,"correct":21},"C","29",true,{"key":23,"text":24,"correct":14},"D","31","D工作的最早开始时间：Max(25+3，21+8，19+7)=29(周)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]