[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92768":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92768,64,1,"单选题","某项工作有两项紧后工作E和 F，E的最迟完成时间是12天．F的最迟完成时间是18天，E的持续时间是7天，F的持续时间是15天，则本工作的最迟完成时间是（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","5",{"key":23,"text":24,"correct":14},"D","6","某项工作的最迟完成时间等于各紧后工作的最迟开始时间的最小值。E工作的最迟开始时间12-7=5(天)；D工作的最迟开始时问18-15=3(天)。最小值为3天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]