[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92758,64,1,"单选题","在网络计划的执行过程中，当某项非关键工作的实际进度拖延，且拖后的时间超过其自由时差时，则必定影响（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目的总工期",false,{"key":16,"text":17,"correct":14},"B","其紧后工作的最迟开始时间",{"key":19,"text":20,"correct":21},"C","其紧后工作的最早开始时间",true,{"key":23,"text":24,"correct":14},"D","其后续工作的最迟完成时间","本题考查自由时差的概念。自由时差的含义为在不影响其紧后工作最早开始的前提下，本工作可以利用的机动时间，那么如果某项非关键工作的实际进度拖延超过了其自由时差，就会影响其紧后工作的最早开始时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]