[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92756":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92756,64,1,"单选题","在工程网络计划中，工作M的持续时间为8天，其最早开始时间是第5天。该工作有三项紧后工作，最迟开始时间分别为第17天、20天、22天。则工作M的总时差是（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":18},"B","4",true,{"key":20,"text":21,"correct":14},"C","6",{"key":23,"text":24,"correct":14},"D","8","(1)工作M的最早完成时间：8+5=13(天)。 (2)工作M的最迟完成时间：Min(17，20，22)=17(天)。 (3)工作M的总时差为其最迟完成时间-其最早完成时间=17-13=4(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]