[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92755,64,1,"单选题","某工程网络计划中，工作A的持续时间为7天，总时差为5天，自由时差为3天。通过计划执行过程检查，发现工作A的实际进度拖延了10天，则将影响工程计划工期（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","10","进度拖延的时间>自由时差时，影响其紧后工作的最早开始时间；进度拖延的时间>总时差时，影响总工期，影响的时长是相应二者的差值。当T作实际进度拖延10天，而总时差为5天时，影响总工期的天数=10—5=5(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]