[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92749":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92749,64,1,"单选题","前锋线比较法步骤中，最后一步是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","绘制时标网络计划图",false,{"key":16,"text":17,"correct":14},"B","绘制实际进度前锋线",{"key":19,"text":20,"correct":14},"C","进行实际进度与计划进度的比较",{"key":22,"text":23,"correct":24},"D","预测工作进度偏差对后续工作及总工期的影响",true,"前锋线比较法步骤如下。 （1）绘制时标网络计划图 （2）绘制实际进度前锋线 （3）进行实际进度与计划进度的比较 （4）预测工作进度偏差对后续工作及总工期的影响",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]