[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92747":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92747,64,1,"单选题","通过改变某些工作间逻辑关系的方法调整进度计划时，应选择( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","具有工艺逻辑关系的有关工作",false,{"key":16,"text":17,"correct":18},"B","超过计划工期的非关键线路上的有关工作",true,{"key":20,"text":21,"correct":14},"C","可以增加资源投入的有关工作",{"key":23,"text":24,"correct":14},"D","持续时间可以压缩的有关工作","此题考查网络计划调整方法。当工程网络计划实施中产生的进度偏差影响到总工期，且有关工作的逻辑关系允许改变时，可以改变关键线路和超过计划工期的非关键线路上的有关工作之间的逻辑关系，达到缩短工期的目的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]