[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92743,64,1,"单选题","双代号时标网络计划中，工作D有四项紧后工作，其工作总时差分别为6周、4周、7周和5周，工作D自由时差为3周，则工作D的总时差是( )周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","8","此题考查双代号时标网路计划总时差计算。在双代号时标网络中，除以终点节点为完成节点的工作外，工作箭线中波形线的水平投影长度表示工作与其紧后工作之间的时间间隔。除以终点节点为完成节点的工作外，工作的自由时差就是该工作箭线中波形线的水平投影长度。除以终点节点为完成节点的工作外，工作的总时差等于其紧后工作的总时差加本工作与该紧后工作之间的时间间隔所得之和的最小值。本题中，工作D与其紧后工作之间的时间间隔为3周，工作D的总时差=min(6+3，4+3，7+3，5+3)=7(周)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]