[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92741,64,1,"单选题","当网络图中有多项结束工作时，应增设一项（ ），作为该网络图的终点节点。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平行工作",false,{"key":16,"text":17,"correct":14},"B","紧前工作",{"key":19,"text":20,"correct":14},"C","紧后工作",{"key":22,"text":23,"correct":24},"D","虚工作",true,"当网络图中有多项结束工作时，应增设一项虚工作（F)，作为该网络图的终点节点。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]