[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92739,64,1,"单选题","在网络计划执行过程中，发现B工作还需工作7天完成，但至该工作最迟完成时间还有4天，则该工作( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超前3天",false,{"key":16,"text":17,"correct":18},"B","影响总工期3天",true,{"key":20,"text":21,"correct":14},"C","影响总工期4天",{"key":23,"text":24,"correct":14},"D","影响总工期7天","此题考查对最迟完成时间的理解。工作的最迟完成时间是指在不影响整个任务按期完成的前提下，本工作必须完成的最迟时刻。本题中，工作B在不影响总工期的前提下，必须完成的最迟时刻还有4天，工作B还需工作7天完成，故工作B使总工期拖后7-4=3(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]