[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92736,64,1,"单选题","在某工程网络计划中，工作H的持续时间为4周，其最早开始时间是第7周。该工作的总时差和自由时差分别为5周和3周。则工作H的最迟完成时间是第( )周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","13",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","16",true,{"key":23,"text":24,"correct":14},"D","17","此题考查最迟完成时间参数计算。工作的最迟完成时间是指在不影响整个任务按期完成的前提下，本工作必须完成的最迟时刻。本题中，工作H的最早完成时间=工作H的最早开始时间+工作H的持续时间=7+4=11(周)；工作H的总时差等于该工作的最迟完成时间与最早完成时间之差，即5=工作H的最迟完成时间-11，故工作H的最迟完成时间=5+11=16(周)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]