[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92734,64,1,"单选题","某工程双代号网络计划中，工作M的最早开始时间是第9天，其持续时间为6天。该工作有三项紧后工作，其最迟开始时间分别为第l7天、第18天和第19天。则工作M的总时差是( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","6","此题考查总时差参数计算。工作M的最早完成时间=工作M的最早开始时间+工作M的持续时间=9+6=15(天)；工作M的最迟完成时间应等于其所有紧后工作最迟开始时间的最小值，故工作M的最迟完成时间为17天；工作M的总时差等于该工作最迟完成时间与最早完成时间之差，即17-15=2(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]