[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92732,64,1,"单选题","（ ）是指在不影响整个任务按期完成的前提下，本工作必须开始的最迟时刻。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最早开始时间",false,{"key":16,"text":17,"correct":14},"B","最早完成时间",{"key":19,"text":20,"correct":21},"C","最迟开始时间",true,{"key":23,"text":24,"correct":14},"D","最迟完成时间","工作的最迟开始时间是指在不影响整个任务按期完成的前提下，本工作必须开始的最迟时刻。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]