[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92726,64,1,"单选题","某工程双代号网络计划中，工作M的最早开始时间为第6天，其持续时间为5天，其紧后工作的最早开始时间和最迟开始时间分别为第14天和第16天，则工作M的自由时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","4",false,{"key":20,"text":21,"correct":18},"C","5",{"key":23,"text":24,"correct":18},"D","6","本题考查的是双代号网络计划时间参数计算。 某项工作的自由时差等于其紧后工作的最早开始时间减去其最早完成时间。 本题中，本作M的最早完成时间＝6+5＝11，其紧后工作的最早开始时间是第14天，则该工作的自由时差为14－11＝3天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]