[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92720,64,1,"单选题","某网络计划执行过程中，发现工作M还需工作9天，但该工作至最早完成时间尚有2天，最迟完成时间有5天，则该工作使总工期( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拖后2天",false,{"key":16,"text":17,"correct":18},"B","拖后4天",true,{"key":20,"text":21,"correct":14},"C","拖后6天",{"key":23,"text":24,"correct":14},"D","拖后8天","此题考查对工作最迟完成时间的理解。工作的最迟完成时间是指在不影响整个任务按期完成的前提下，本工作必须完成的最迟时刻。工作M如果能在最迟完成时间完成，则不影响总工期；比最迟完成时间晚几天，该工作就会使总工期拖延几天。则该工作使总工期拖后9-5=4(天)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]