[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92718":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92718,64,1,"单选题","在绘制双代号网络图时，一般应遵循的基本规则中不正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","网络图必须按照已定的递进关系绘制",true,{"key":16,"text":17,"correct":18},"B","网络图中严禁出现从一个节点出发，顺箭头方向又回到原出发点的循环回路",false,{"key":20,"text":21,"correct":18},"C","网络图中严禁出现双向箭头和无箭头的连线",{"key":23,"text":24,"correct":18},"D","网络图中严禁出现没有箭尾节点的箭线和没有箭头节点的箭线","此题考查双代号网络计划绘制规则。绘制双代号网络图遵循的基本规则：①网络图必须按照已定的逻辑关系绘制；②网络图中严禁出现从一个节点出发，顺箭头方向又回到原出发点的循环回路；③网络图中的箭线应保持自左向右的方向，不应出现箭头指向左方的水平箭线和箭头偏向左方的斜向箭线；④网络图中严禁出现双向箭头和无箭头的连线；⑤网络图中严禁出现没有箭尾节点的箭线和没有箭头节点的箭线；⑥严禁在箭线上引入或引出箭线；⑦应尽量避免网络图中工作箭线的交叉；⑧网络图中应只有一个起点节点和一个终点节点；⑨网络图中的节点都必须有编号，其编号严禁重复，并应使每一条箭线上箭尾节点编号小于箭头节点编号。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]