[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92717,64,1,"单选题","双代号网络计划中的节点表示( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作",false,{"key":16,"text":17,"correct":14},"B","工作的开始",{"key":19,"text":20,"correct":14},"C","工作的结束",{"key":22,"text":23,"correct":24},"D","工作的开始或结束",true,"此题考查双代号网络计划相关内容。双代号网络计划又称箭线式网络计划，它是以箭线及其两端节点编号表示工作的进度计划。同时，节点又表示工作的开始或结束以及工作之间的连接状态。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]