[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92711,64,1,"单选题","下列关于自由时差和总时差的说法错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差为零，总时差必定为零",true,{"key":16,"text":17,"correct":18},"B","总时差为零，自由时差必定为零",false,{"key":20,"text":21,"correct":18},"C","在不影响总工期的前提下，本工作的机动时间为总时差",{"key":23,"text":24,"correct":18},"D","在不影响紧后工作最早开始时间的前提下，本工作的机动时间为自由时差","此题考查对工作总时差和自由时差的理解。工作的总时差是指在不影响总工期的前提下，本工作可以利用的最大机动时间。工作的自由时差是指在不影响其紧后工作最早开始时间的前提下，本工作可以利用的机动时间。从总时差和自由时差的定义可知，对于同一项工作而言，自由时差不会超过总时差。当工作的总时差为零时，其自由时差必然为零。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]