[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92709,64,1,"单选题","除以网络计划起点节点为开始节点的工作外，其他工作的最早开始时间等于其紧前工作( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最早完成时间的最小值",false,{"key":16,"text":17,"correct":18},"B","最早完成时间的最大值",true,{"key":20,"text":21,"correct":14},"C","最迟完成时间的最小值",{"key":23,"text":24,"correct":14},"D","最迟完成时间的最大值","此题考查工作最早开始时间。在双代号网络计划中，以网络计划起点节点为开始节点的工作，当未规定最早开始时间时，其最早开始时间为零；其他工作的最早开始时间应等于其紧前工作最早完成时间的最大值",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]