[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92702,64,1,"单选题","在工程双代号网络计划中，某项工作的最早完成时间是指其( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在各紧前工作全部完成后，工作有可能开始的最早时刻",false,{"key":16,"text":17,"correct":14},"B","开始节点的最早时间与工作自由时差之和",{"key":19,"text":20,"correct":21},"C","在各紧前工作全部完成后，本工作有可能完成的最早时刻",true,{"key":23,"text":24,"correct":14},"D","开始节点的最早时间与工作总时差之和","此题考查对工作最早完成时间的理解。工作的最早完成时间是指在其所有紧前工作全部完成后，本工作有可能完成的最早时刻。工作的最早完成时间等于本工作的最早开始时间与其持续时间之和。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]