[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92686,64,1,"单选题","相对于某工作而言 ，从网络计划起点节点开始，顺箭头方向经过一系列箭线与节点到达该工作为止的各条通路上的所有工作，都称为该工作的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先行工作",true,{"key":16,"text":17,"correct":18},"B","后续工作",false,{"key":20,"text":21,"correct":18},"C","紧前工作",{"key":23,"text":24,"correct":18},"D","平行工作","相对于某工作而言 ，从网络计划起点节点开始，顺箭头方向经过一系列箭线与节点到达该工作为止的各条通路上的所有工作，都称为该工作的先行工作。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]