[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92684,64,1,"单选题","建设工程网络计划编制程序中，紧接“绘制网络图阶段”之后的程序是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划准备阶段",false,{"key":16,"text":17,"correct":18},"B","计算时间参数阶段",true,{"key":20,"text":21,"correct":14},"C","网络计划优化阶段",{"key":23,"text":24,"correct":14},"D","网络计划执行阶段","此题考查工程网络计划技术应用程序。工程网络计划技术应用程序可分为五个阶段：①计划准备阶段；②绘制网络图阶段；③计算时间参数阶段；④网络计划优化阶段；⑤网络计划执行阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]