[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92682,64,1,"单选题","网络计划应用程序中，绘制网络图阶段不包括( )步骤。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程项目分解",false,{"key":16,"text":17,"correct":14},"B","关系逻辑分析",{"key":19,"text":20,"correct":21},"C","计算工作持续时间",true,{"key":23,"text":24,"correct":14},"D","绘制网络图","此题考查绘制网络图阶段内容。绘制网络图阶段的内容主要包括：工程项目分解、分析逻辑关系和绘制网络图。选项C属于计算时间参数阶段的内容。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]