[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92677":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92677,64,1,"单选题","建设工程网络计划编制程序中，属于绘制网络图阶段的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定网络计划目标",false,{"key":16,"text":17,"correct":18},"B","分析逻辑关系",true,{"key":20,"text":21,"correct":14},"C","计算工作持续时间",{"key":23,"text":24,"correct":14},"D","优化网络计划","此题考查绘制网络图阶段内容。绘制网络图阶段的内容主要包括：工程项目分解、分析逻辑关系和绘制网络图。选项A属于计划准备阶段的内容。选项c属于计算时间参数阶段的内容。选项D属于网络计划优化阶段的内容。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]