[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92663,64,1,"单选题","下列不属于建设工程监理目标控制任务的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程质量控制任务",false,{"key":16,"text":17,"correct":14},"B","工程造价控制任务",{"key":19,"text":20,"correct":21},"C","工程环境控制任务",true,{"key":23,"text":24,"correct":14},"D","工程进度控制任务","任何工程都有质量、造价、进度三大目标，工程监理单位受建设单位委托，需要协调处理三大目标之间关系、确定与分解三大目标，并采取有效措施控制三大目标。目标控制任务有：①工程质量控制任务，它是指通过采取有效措施，在满足工程造价和进度要求的前提下，实现预定的工程质量目标；②工程造价控制任务，它是指通过采取有效措施，在满足工程质量和进度要求的前提下，力求使工程实际造价不超过预定造价目标；③工程进度控制任务，它是指通过采取有效措施，在满足工程质量和造价要求的前提下，力求使工程实际工期不超过计划工期目标。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]