[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92615":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92615,64,1,"单选题","关于建设工程项目目标主动控制的说法，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","主动控制是一种反馈式控制",false,{"key":16,"text":17,"correct":14},"B","主动控制是一种闭环式控制",{"key":19,"text":20,"correct":14},"C","主动控制是一种事后控制",{"key":22,"text":23,"correct":24},"D","主动控制是一种事前控制",true,"主动控制是一种开环式控制；主动控制是一种事前控制；主动控制是一种前馈控制。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]