[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92601,64,1,"单选题","建设工程监理工作的主要内容有：①编制建设工程监理规划；②制定监理实施细则：③确定总监理工程师和成立项目监理机构；④开展监理工作；⑤提交监理档案和工作总结：⑥参与验收并签署监理意见。其正确的实施程序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①-②-③-④-⑤-⑥",false,{"key":16,"text":17,"correct":18},"B","③-①-②-④-⑥-⑤",true,{"key":20,"text":21,"correct":14},"C","⑧-②-①-④-⑤-⑥",{"key":23,"text":24,"correct":14},"D","⑥-⑤-④-③-②-①","本题考查的是建设工程监理的程序。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]