[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92563,64,1,"单选题","关于主动控制与被动控制的说法,正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由于主动控制比被动控制的效果好，因而应采取主动控制",false,{"key":16,"text":17,"correct":14},"B","由于建设工程实施中有许多风险因素不可预见和防范，因而只能采取被动控制",{"key":19,"text":20,"correct":14},"C","进行项目目标控制应以主动控制为主、被动控制为辅",{"key":22,"text":23,"correct":24},"D","只有将主动控制与被动控制有机融合，才能使控制更为有效",true,"选项D属于正确的主动控制与被动控制的关系。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]