[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92520":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92520,64,1,"单选题","下列事项中，总监理工程师可以委托总监理工程师代表的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","主持编写项目监理规划",false,{"key":16,"text":17,"correct":14},"B","审核签认竣工结算",{"key":19,"text":20,"correct":14},"C","组织工程竣工预验收",{"key":22,"text":23,"correct":24},"D","检查监理人员的工作",true,"此题考查总监理工程师可以委托总监理工程师代表的事项。总监理工程师不得将下列工作委托给总监理工程师代表：①组织编制监理规划，审批监理实施细则；②根据工程进展及监理工作情况调配监理人员；③组织审查施工组织设计、（专项)施工方案；④签发工程开工令、暂停令和复工令；⑤签发工程款支付证书，组织审核竣工结算；⑥调解建设单位与施工单位的合同争议，处理工程索赔；⑦审查施工单位的竣工申请，组织工程竣工预验收，组织编写工程质量评估报告，参与工程竣工验收；⑧参与或配合工程质量安全事故的调查和处理。选项A、B、C均为总监理工程师不能委托给总监理工程师代表的工作。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]