[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92467,64,1,"单选题","下列关于工程暂停及复工处理中表述不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总监理工程师签发工程暂停令，应事先征得建设单位同意",false,{"key":16,"text":17,"correct":14},"B","总监理工程师在紧急情况下未能事先报告时，应在事后及时向建设单位作出书面报告",{"key":19,"text":20,"correct":21},"C","当暂停施工原因解除、具备复工条件时，施工单位提出复工申请的，项目监理机构应审查施工单位报送的有关材料，符合要求后的总监理工程师应及时签署审查意见批准签发工程复工令",true,{"key":23,"text":24,"correct":14},"D","当暂停施工原因解除、具备复工条件时，施工单位未提出复工申请的，总监理工程师应根据工程实际情况指令施工单位恢复施工。","复工审批或指令。当暂停施工原因解除、具备复工条件时，施工单位提出复工申请的，项目监理机构应审查施工单位报送的工程复工报审表及有关材料，符合要求后，总监理工 程师应及时签署审查意见，并应报建设单位批准后签发工程复工令;施工单位未提出复工申请 的，总监理工程师应根据工程实际情况指令施工单位恢复施工。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]