[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92438":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92438,64,1,"单选题","项目监理机构系统外部协调分为近外层协调和远外层协调，建设单位与近外层关联单位一般()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","无合同关系",false,{"key":16,"text":17,"correct":14},"B","有委托关系",{"key":19,"text":20,"correct":21},"C","有合同关系",true,{"key":23,"text":24,"correct":14},"D","有利害关系","此题考查工程监理机构组织协调。项目监理机构可采用会议、交谈、书面方法进行组织协调。组织协调内容可分为系统内部(项目监理机构协调和系统外部协调两大类，系统外部协调又分为系统近外层协调和系统远外层协调。近外层和远外层的主要区别是，建设单位与近外层关联单位之间有合同关系，与远外层关联单位之间没有合同关系。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]