[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92429":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92429,64,1,"单选题","项目监理机构与设计单位的协调属于项目监理机构的()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","内部协调",false,{"key":16,"text":17,"correct":14},"B","近内部协调",{"key":19,"text":20,"correct":21},"C","近外层协调",true,{"key":23,"text":24,"correct":14},"D","远外层协调","此题考查项目监理机构组织协调。项目监理机构组织协调内容可分为系统内部（项目监理机构）协调和系统外部协调两大类，系统外部协调又分为系统近外层协调和系统远外层协调。近外层和远外层的主要区别是，建设单位与近外层关联单位之间有合同关系，与远外层关联单位之间没有合同关系。①项目监理机构内部协调，主要是指项目监理机构内部的人际关系协调、组织关系协调和需求关系协调等。②项目监理机构外部协调，主要是指项目监理机构与建设单位的协调、项目监理机构与施工单位的协调、项目监理机构与设计单位的协调、项目监理机构与政府部门及其他单位的协调等。建设单位与设计单位有合同关系，故属于近外层协调。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]