[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92407,64,1,"单选题","安装工程风险最大的阶段是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工阶段",false,{"key":16,"text":17,"correct":14},"B","使用阶段",{"key":19,"text":20,"correct":21},"C","试车、考核和保证阶段",true,{"key":23,"text":24,"correct":14},"D","维护阶段","建筑工程保险的标的从开工以后逐步增加，保险额也逐步提高，而安装工程一切险的保险标的一开始就存放于工地，保险人一开始就承担着全部货价的风险。在机器设备安装好后，试车、考核和保证阶段风险最大。由于风险集中，试车期安装工程一切险的保险费通常要占整个工期保费的1\u002F3左右。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]