[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92389,64,1,"单选题","在工程项目决策阶段，属于业主或开发商承担的风险是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计疏忽与错误",false,{"key":16,"text":17,"correct":14},"B","报价策略选择失当",{"key":19,"text":20,"correct":21},"C","政策风险",true,{"key":23,"text":24,"correct":14},"D","施工方案选择失当","由于项目决策阶段是研究工程建设必要性、技术可行性、经济合理性的关键时期，该阶段涉及的内外部环境复杂，风险因素众多，业主或开发商承担的风险一般包括：①国家宏观政策、产业政策及区域发展规划变动所引起的政策风险；②项目产品需求、价格和竞争等方面变化引起的市场风险；③国家和地区的居民教育程度和文化水平、风俗习惯等引起的社会文化风险；④与投资有关的法律风险；⑤投资决策组织机制、责任机制、动力机制、控制机制等方面不健全带来的内部决策机制风险等。由于项目决策阶段存在大量不确定因素，业主或开发商很容易做出错误的决定，产生风险损失。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]