[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92388,64,1,"单选题","下列关于风险管理过程的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","风险管理过程由风险估计、风险应对活动组成",false,{"key":16,"text":17,"correct":14},"B","风险估计包括风险识别和风险评价",{"key":19,"text":20,"correct":14},"C","风险评价包括风险识别和风险估计",{"key":22,"text":23,"correct":24},"D","工程风险识别是风险管理的第一步",true,"ABC三项，风险管理流程内容包括：①工程风险识别；②工程风险估计；③工程风险评价；④工程风险应对；⑤工程风险监控。这些流程之间既存在联系，也相互区别。D项，工程风险识别是风险管理的第一步，能否将工程潜在的重大风险都识别出来，决定了风险管理效果。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]